EPSRC logo

Proposal Processing Panel

For the EPSRC Equipment Business Case panels, the capital costs awarded are added to institutional equipment accounts. Therefore, the information recorded below does not accurately reflect the amounts awarded at the panel meeting. For a record of awards made by the EPSRC Equipment Business Case panels see:
https://epsrc.ukri.org/research/ourportfolio/themes/researchinfrastructure/subthemes/equipment/supported/.

Panel Name: EPSRC Equipment Business Case - March 2014
Date of Panel: 05 March 2014
Panel Contact: Hanlon, Tracy


In exceptional circumstances, panel membership may change at a late stage. Such changes may not be reflected in the membership below.
The research organisations listed are current and are not necessarily those that the panel member was affiliated with at the time of the panel.
Under no circumstances should the panel members be contacted to discuss meeting details or outcomes.

All enquiries must be directed to the EPSRC panel contact.

Panel Members:
McCann, Professor HUniversity of EdinburghPanel Chairperson
Charlton, Professor MSwansea University 
Freer, Professor RThe University of Manchester 
Marsden, Professor SPUniversity of Leeds 
Spearing, Professor SMUniversity of Southampton 
Hanlon, TracyEngineering and Physical Sciences Research CouncilPanel Contact

 Outcomes Summary By Number
Funding rates may change over time until all decisions are finalised
Funding Priority ListFundedUnfundedReferred to a later panelDecision still awaitedFunding rate
(% of grant number)
Standard4510 44
 Including:
Main List 3 5 1 0 37
XFEL 1 0 0 0 100
Spacer Image8626 Please click on relevant Funding Priority List for a full rank ordered list.

 Outcomes Summary By Value (£)
Funding rates may change over time until all decisions are finalised
Funding Priority ListFundedUnfundedReferred to a later panelDecision still awaitedFunding rate
(% of grant value)
Standard470,8628,130,54210,5270 5
 Including:
Main List 335,932 8,130,542 0 0 3
XFEL 145,457 0 0 0 100
Spacer Image7904 Please click on relevant Funding Priority List for a full rank ordered list.